Phases 4 and 5 of Sangachal onshore plant to be operational by late September

Phases 4 and 5 of Sangachal onshore plant to be operational by late September
# 21 August 2009 15:10 (UTC +04:00)
Baku. Nijat Mustafayev – APA-Economics. At Sangachal, work has progressed on completion and commissioning of the produced water facilities as part of the Sangachal Terminal Expansion Programme (STEP), said BP-Azerbaijan.

“We completed the early export phases (1-3) of the project in late 2008 and started exporting water to Central Azeri in March 2009 and re-injection into the ACG field in early July 2009. Phases 4 and 5 of the onshore plant should be operational by the end of September 2009,” said the company.

The new gas dew point control unit (DPCU2) for ACG associated gas has been completed and is being commissioned now with start-up of the plant expected in September.


#
#

THE OPERATION IS BEING PERFORMED