Military units in the Kalbajar region were provided with electric energy, Azerishig told APA-Economics.
Electric supply of military units and battalions was completed by installing a total of 8 Kit Transformer Stations in Veng, Baglitepe, Gamishli, Chaykand, and Gilincli villages.
In general, 6.2 km of 10 kV cable, more than 2,500 meters of 0.4 kV cable power line, more than 1.5 km of 10 kV overhead power transmission line were laid for the military units with complete power supply. As a continuation of the works done, a 10 kV overhead power transmission line was restored from a 110/35/10 kV “Kalbajar” substation in the direction of Vang, Baglipeya villages.