BP-Azerbaijan to drill several wells at Deepwater Guneshli

BP-Azerbaijan to drill several wells at Deepwater Guneshli
# 29 May 2009 16:05 (UTC +04:00)
Baku. Nijat Mustafayev – APA-Economics. BP-Azerbaijan plans to drill several wells at Deepwater Guneshli this year.

Pre-drilled wells tie-in to the platform at Deepwater Guneshli is complete and 10 pre-drilled wells are in operation, said BP-Azerbaijan.

“Drilling work for E11 production well is under way and is slated for completion in October 2009. Besides, E12 production well will be drilled this year,” said the company.