Enlargement of Baku Metro to cost AZN 8.9 bln

Enlargement of Baku Metro to cost AZN 8.9 bln
# 10 September 2012 12:58 (UTC +04:00)
To him, according to perspective development plan of metro, 53 new stations, 84.3 km new metro line or more than 165 km tunnels will be launched: ‘1 km metro line costs AZN 100-110. It includes station, train, all cables’.

Resulov noted that 28 May station will start to operate on September 15: ‘In connection with new academic year, new station will start to work on September 15, at 6.00. 4 escalators have been installed. 2 of them are 1-m-widht, other 2 – 80 centimeters. And it is also is a novelty’.

Moreover, repair of old stations will be continued, too. One of the Sahil, Nizami or Khatayi stations will be repaired in 2013.
#
#