Bank Of Baku

Azerbaijani President attends opening of three-level road junction

Azerbaijani President attends opening of three-level road junction
# 04 October 2011 11:58 (UTC +04:00)
According to APA-Economics, the president was informed about technical indicators of junction. Length of the bridge is 220 m, width – 23.5 m, The bridge has four traffic paths. Length of piling is 13-16 m, diameter – 1,200. Length of the biggest hill of the bridge is 75 m, considered seismic sustainability – 9 magnitudes.

The president was informed that, tunnel part of the junction was constructed in 15 months. Total length of tunnel is 400 m, length of closed part – 55 m. Capacity of rain waters 530 m³.

The junction will provide the traffic in the direction from Heydar Aliyev International Airport to Mardakan, Shuvalan and Buzovna settlements.

Head of state expressed his consent and recommended.