The procurement of necessary equipment for the Shafag Solar Power Plant project being implemented in Azerbaijan's Jabrayil district has been largely completed, while construction work is progressing as planned, Bakhtiyar Aslanbayli, bp's Vice President for the Caspian, Central Asia and Türkiye region, told journalists, APA-Economics reports.
According to him, solar panels, converters and other necessary equipment have already been purchased and delivered to the site as part of the project.
Bakhtiyar Aslanbayli noted that the installation of piles, placement of panels and mechanical work have been completed in one section of the plant's site. Mainly electrical installation work remains in that section.
Mechanical work is continuing in another section of the site.
The Vice President said that certain logistical difficulties, as well as equipment transportation and supply processes, could affect the project schedule. However, no serious problems are currently being observed.
According to him, Azerenergy has also carried out work related to the substation for the project, and preparations in this area have been completed.
Responding to a question about whether the first phase of the project would be completed by the middle of next year, Bakhtiyar Aslanbayli said that work was continuing toward this goal.