Construction has begun on one of the largest and highest-voltage transmission lines in Azerbaijan's energy system. As part of the second phase of the "Azerbaijan Scaling-Up Renewable Energy Project – AZURE," construction has started on a 235-kilometer-long, 500-kilovolt high-voltage transmission line from Mingachevir to Navahi, APA-Economics reports.
The 500-kilovolt transmission line, being built at the country's highest existing voltage level, is of strategic importance for expanding the transmission capacity of the energy system and ensuring the safe and reliable integration of newly established renewable energy sources into the national power grid.
The project will also ensure the formation of a 500-kilovolt ring-shaped power transmission network covering Azerbaijan's western, central, and eastern regions, enabling electricity to be transmitted over long distances with lower losses. In addition, it will expand opportunities for regulating frequency and power balance in the energy system and managing electricity flows more flexibly.
It should be noted that significant infrastructure work has already been carried out under the first phase of the AZURE project. Construction of the new 500/300-kilovolt Navahi Green Energy Hub, one of the country's largest substations, has been completed using AzerEnerji's internal resources and funds partially allocated from the state budget.
The installation of a 500-kilovolt transmission line from Navahi to Absheron, as well as 330-kilovolt transmission lines to the Bilasuvar and Banka solar power plants, with a total length exceeding 245 kilometers, has also been completed. As a result, the necessary infrastructure has been established to connect both solar power plants to the country's unified energy system, and the planned obligations in this regard have been fulfilled.
The second phase of the AZURE project, supported financially by the World Bank, envisages equipping the Navahi Green Energy Hub with transformers and reactors, constructing a new 500-kilovolt transmission line from Mingachevir to Navahi, and installing 330-kilovolt transmission lines toward Alat, Absheron, and Gobu.
Construction of the 500-kilovolt Mingachevir–Navahi transmission line has already begun, while construction of the three 330-kilovolt transmission lines is expected to start in the near future.
Thus, the AZURE project will make a significant contribution to realizing Azerbaijan's renewable energy potential, developing high-voltage transmission infrastructure, and further strengthening the country's energy security.