The reactor of the Armenian NPP will be stopped on Friday for repairs, APA reports quoting RÄ°A Novosti.
On June 1, the reactor (according to the standard annual repair campaign program) and turbine unit No. 3 (for partial modernization) will be shut down.
On August 1, the launch of a power unit with a partially modernized turbo unit No. 4 is envisaged. Commissioning of turbo unit No. 3 is planned for December 1 of this year after completion of its modernization.
As a result of the works planned for 2018, a significant increase in the output of the power unit is expected.