TAP pipe deliveries complete

TAP pipe deliveries complete
# 16 October 2017 12:27 (UTC +04:00)

On 10 October 2017, the last shipment of steel line-pipes for the construction of the Trans Adriatic Pipeline (TAP) arrived in Thessaloniki, Greece, marking the completion and final delivery of all line-pipes to TAP’s host countries.

According to TAP consortium, the transport of 55,000 TAP pipes and bends was completed in approximately one year and a half. The first pipes arrived in Durrës, Albania in April 2016 and deliveries to Greece started one month later, in May 2016.


Approximately 55,000 pipes are used to build TAP (32,000 in Greece; 13,000 in Albania; 9,150 offshore and 670 in Italy). The pipes were manufactured by Corinth Pipeworks (Greece) and Salzgitter Mannesmann International (Germany).

#
#