Over 22,000 people involved in Shah Deniz Stage 2 project - BP

 Over 22,000 people involved in Shah Deniz Stage 2 project - BP
# 24 May 2016 14:40 (UTC +04:00)

Baku - APA-Economics. In the first quarter of 2016, implementation of the Shah Deniz Stage 2 project continued successfully.

According to BP-Azerbaijan, the project is now over 70% complete in terms of engineering, procurement and construction, and remains on target for first gas from Shah Deniz Stage 2 in 2018.

Project activities continue at all offshore and onshore sites and fabrication yards of the country including the Sangachal Terminal, ATA (AMEC/Tekfen/Azfen) yard near Baku, Baku Deepwater Jackets Factory and along the pipeline route.

The pipe-lay barge Israfil Huseynov has installed about 40 kilometers of the 32-inch subsea export pipeline in accordance with the plan.

In the first quarter of 2016, BP also started commissioning activities on the two Shah Deniz 2 topside units at the ATA yard and nearly all of the 50 living quarter modules have already been installed on the quarters and utilities platform.

In the first quarter of 2016, over 22,000 people were involved in construction activities across all main contracts in Azerbaijan and over 80% of them were Azerbaijani nationals.

#
#